Building A New Pool | Buying a New Pool
BUILDING A NEW POOL
Step 1: Excavation
1. Remove fence when necessary
2. Remove concrete walks and patios if called for in the contract.
3. Set the pool beam elevation and grade with a laser level.
4. Lay out the pool in accordance with the dimensions on the technical plan.
5. Excavate pool and remove soil from job-site.
6. Hand shape skimmers, lights, steps, loveseats, and benches.
7. Hand carve bowl and break.
8. Final trim and finish work.
9. Unless provided for in the contract moving or repairing underground utilities or sprinkler systems is the homeowner’s responsibility.
Step 2: Plumbing
The two basic functions of swimming pool plumbing are to circulate and filter the water. The plumbing system in a swimming pool is self-contained and under normal operation does not need city water (except to fill the pool) or the sanitary sewer system (except for backwash).
Skimmers : Skim the surface of the water and remove floating debris. The size and design of the pool will dictate the number of skimmers needed.
1.) Minimum of (1) skimmers in each pool unless larger size pool.
2.) Plumbed and valved separately using 2″ PVC.
Main Drains : Draw water from the floor of the pool for circulation
1.) Divided into (2) openings with anti-vortex covers for safety as required by city codes
2.) Plumbed and valved separately using 2″ PVC.
Returns : Returns water back to the pool from equipment and push debris toward the skimmers.
1.) Minimum of 3 – 4 returns in each pool
2.) Plumbed using 1.5″ PVC.
The system operates in the following manner: a pump pulls water from the main-drain and the skimmer through a leaf trap and into the pump itself. The water is then pushed through the main filter chlorinator, through the heater (if applicable), and the back into the pool through the returns.
Step 3: Steel Construction
Steel rebar is 40-A615, in accordance with Florida steel grading system.
1. Steel reinforcing bars, (rebar), are placed on 12″ centers each way through vertical walls and floor of the pool and 6″ depth over 7″ centers in transitional areas and stress points.
2. Steel is secured by sixteen gauge ties.
Step 4: Gunite
During the gunite process pool depths, elevations and dimensions are set. Also pool benches and steps are hand shaped and formed.
1. Pool light niches and electrical conduit are installed.
2. Gunite will be 6″ thick at walls and floor of the pool and 6″ thick at transitional areas.
3. Broom finishing the gunite creates a rough texture allowing the maximum adherence of plaster.
4. Equipment pad is installed at deck pour.
5. Homeowner should water the gunite shell at least twice a day for seven days. This allows the gunite to cure properly.
Step 5: Tile & Coping
1. Many tile and stone selections are available. We ask that you make your selection as soon as possible.
2. Special grout and mortar mixtures are used to prevent water from seeping through and eroding it’s base.
Step 6: Electrical
1. 120 volt GFCI protection is installed on all pool lights.
2. Brass conduit is used on all light fixtures.
3. Second timer may be added for light.
4. The pool equipment is placed on a separate circuit to avoid an overload on any existing household circuit.
5. All metal within five feet of the water’s edge will be bonded (grounded).
Step 7: Decking
The concrete swimming pool deck is poured around the pool after tile, stone, coping or brickwork is done. Decking usually takes three days to place. The first day, the area to be decked is formed. The second day an electrical bond inspection is performed by the respective city or county and the deck is poured on the third day in most cases.
1. 3.5″ – 4″ concrete thickness.
2. 6″ – 8″ cushion sand.
3. Fibermesh added to concrete mix.
Step 8: Plaster
Important! A newly plastered pool cures in 10 – 14 days. Landscape debris and dirt that comes into contact with the plaster can leave a stain.
1. The interior of the pool is washed to remove all debris.
2. All fittings are installed.
3. Light are installed.
4. Tile is cleaned.
5. Pool is plastered and hand troweled with homeowner choice of aggregate finish.
Step 9: Start Up
1. After the pool is filled with water start up chemicals are added.
2. Deck is acid washed and final stain installed.
3. Mastic is installed between the coping and the decking.
4. Plumbing is labeled.
5. Maintenance equipment is delivered and cleaning system is installed.
6. The customer is walked through and trained on operation of all equipment.
Enjoy your new custom pool !
POOL BUYING PROCESS
Cool Pools will NOT pressure you into buying!
We understand that buying a swimming pool is a big decision for any family. We also know that some families take weeks, months, or even years to make a final decision. We’re okay with that. We’ll help you whenever we can, but we will never try to pressure you into a sale. At all stages of the buying process, you are in control. Here is our process:
- Think about what kind of pool you want
- Get some expert advice
- Get a preliminary design and bid
- Fine-tune your design
- Decide if you want to buy this pool
1. Think about what kind of pool you want
- Review our website and our portfolio. Make a note of any particular pools or water features that you like.
- Feel free to look at our competitors’ websites as well. (They’ve never built anything we can’t build!)
- If you see a pool in a magazine and book or newspaper, save a copy of that too.
2. Get some expert advice
- Telephone – we can discuss some ideas right over the phone if you like.
- Backyard meeting – one of our designers will be happy to look at your backyard, and share some ideas with you.
3. Get some expert advice
- If you’ve got an idea of what you’re looking for, our designers can create a custom design for you.
- If you have a specific budget in mind, let the designer know, so that he can recommend the appropriate features and options.
4. Fine-Tune Your Design
- You may want to add or remove or certain features
- You can choose your tile choices, deck choices and other specific features at this time.
5. Decide if you want this pool
- a simple proposal outlines exactly what your new pool is going to look like, and what it’s going to cost
- small down payment – we can reserve your build slot with a simple $1000 good-faith down payment
- schedule your start date – it’s time to decide when you want the process to begin
It normally takes between 45 and 75 days to complete your new pool, depending on weather and the complexity of the project.
Financing provided by Eagle Bank. Click below to download loan application.
LOAN APPLICATION -

